Stella power stations


The Stella power stations were a pair of now-demolished coal-fired power stations in the North East of England that were a landmark in the Tyne valley for over 40 years. The stations stood on either side of a bend of the River Tyne: Stella South power station, the larger, near Blaydon in Gateshead, and Stella North power station near Lemington in Newcastle. Their name originated from the nearby Stella Hall, a manor house close to Stella South that by the time of their construction had been demolished and replaced by a housing estate. They operated from shortly after the nationalisation of the British electrical supply industry until two years after the Electricity Act of 1989, when the industry passed into the private sector.
These sister stations were of similar design and were built, opened, and closed together. Stella South, with a generating capacity of 300 megawatts, was built on the site of the Blaydon Races, and Stella North, with a capacity of 240 MW, on that of the former Lemington Hall. They powered local homes and the many heavy industries of Tyne and Wear, Northumberland and County Durham. The large buildings, chimneys and cooling towers were visible from afar. Their operation required coal trains on both sides of the river to supply them with fuel and river traffic by flat iron barges to dump ash in the North Sea. After their closure in 1991, they were demolished in stages between 1992 and 1997. Following the stations' demolition, the sites underwent redevelopment: the North site into a large business and industrial park, the South into a housing estate.

History

Development

The British demand for electricity increased after the Second World War. In the North East of England this led to the expansion of existing power stations at Dunston and Billingham in the late 1940s, the two new Stella power stations, and the construction of two more large stations built at Blyth later in the 1960s. This new generating capacity quickly met the demand for power. The British Electricity Authority were granted permission to construct the Stella North and Stella South power stations in 1951. The two stations were originally projected to cost around £15,000,000.
The site chosen for Stella North was the Newburn Haugh, which was the site of Lemington Hall. Lemington Hall was demolished in 1953 during the construction of Stella North. Stella South was built on the Stella Haugh, the site of the Battle of Newburn in 1640. A cannonball from the battle was on display in the South station for many years, after having been dredged from the river bed. Between 1887 and 1916, the Stella Haugh had been the site of the annual Blaydon Races, which stopped after a riot broke out following allegations of race fixing. Just before the construction of the South station the haugh had two uses. Blaydon Rugby Club's ground had been there since 1893, but in 1950 it was compulsorily purchased by the British Electricity Authority for £1,000. The club moved to a new ground in Swalwell, which it still uses. Newcastle University Boat Club had owned a boathouse on the site since 1929, but in 1951 the British Electricity Authority requisitioned it, forcing the club to move upstream to its current location in Newburn.
The addition of various power lines was needed to connect the power stations to the National Grid. These included a 275 kilovolt connection from Stella to West Melton, and another 275 kV connection from Stella to Carlisle. The towers for these connections were to stand at, rather than the towers of the existing grid system. The line from Stella to Carlisle, which was to consist of 250 towers spaced at 320 meters over a distance of around, came up against opposition when first proposed. The Northumberland County Planning Authority launched a public enquiry in 1951, and Hexham Rural District Council held a meeting. The Ministry of Agriculture and other outdoor associations voiced their concerns, as it was feared that the line would interfere with good farming land. An alternative route was proposed, but in view of its additional cost of £72,000 it was turned down, and the Ministry of Fuel and Power gave the line the go-ahead.

Construction

Both of the stations were designed by Newcastle upon Tyne-based architects L J Couves & Partners, and construction work began in 1951. The Cleveland Bridge Company were contracted to construct the steel frames for the stations' main buildings, including their turbine halls, boiler houses, workshops and stores buildings. Various other companies were contracted for the construction of other parts of the station. Sir Robert McAlpine & Sons were contracted for site clearance, provision of the foundations for the main and ancillary buildings, as well as the diversion of streams and sewers. Davenport Engineering Co. were responsible for the construction of the North station's cooling towers, as well as the stations' ancillary buildings. P.C. Richardson & Co. built the stations' brick chimneys. Aiton & Co. installed the stations' low-pressure piping equipment. Underwater electrical work was carried out by British Royal Navy frogman Lionel "Buster" Crabb, chosen for the dangerous job because he wore a rubber diving suit at a time when most divers used canvas.
The first generating sets of the stations became operational on 20 December 1954. However, it was not until 1956 that all four of the North station's units were commissioned, and 1957 before all five of the South station's units generated electricity. The cost of the two stations in total came to around £40,500,000.
On the morning of 14 December 1955, during the stations' construction, switchgear exploded in the South station's substation, closing down the generators. Dunston power station could not take the extra load and it also shut down, creating a total blackout on Tyneside. Around 400,000 people were affected by the fault, including 20,000 miners trapped in over a hundred collieries. Power was fully reconnected by that evening. but the failure caused an interruption of work and services worth more than £1,000,000, as well as the loss of 300 megawatts of electricity.

Post-commissioning

Although developed by the British Electricity Authority, the stations were first operated by the Central Electricity Authority, following the Electricity Reorganisation Act 1954. From 1957 they were operated by the Central Electricity Generating Board, following the Electricity Act 1957.
In 1961, Stella North was presented with the Hinton Cup, the CEGB's "good house keeping trophy". The award was presented by Sir Christopher Hinton, the first chairman of the CEGB. The station's achievement was attributed to the fact the station's annual efficiency had never been less than 29.1%. The station also won the North East regional award for the second year in a row in 1961. In March 1967, Stella South's male first aid team won a national first aid competition in Harrogate, organised by the CEGB. Over 150 teams took part.
In 1966, Stella North was at the centre of a legal case in which three men were found guilty of conspiracy to defraud after trying to sell the CEGB poor quality coal when contracted to deliver high quality coal. The three men involved were D.C.P. Brooksbank, a salesman for a coal firm; J.W. Patterson, a sampler at the power station, and M. Ridley, a contractor. Their scheme was for Patterson to substitute samples of reasonably good coal for the samples of poor coal taken from the lorries. However they were found out only two days after starting the scheme, when a foreman at the station saw Patterson dropping a bag of cement into the sampling bin, and reported the incident. Ridley was found to have planned the fraud, and was jailed for a year, while Brooksbank was fined £150 and Patterson £75.

Design and specification

The main visible features of the stations were their large boiler houses, turbine halls, cooling towers and pairs of chimneys; other facilities on both sites included offices, coal sorting areas, small fire stations and workshops. The power stations had the "brick-cathedral" style of design popular for power stations in the 1930s and 1940s and, as of 2009, still tenuously surviving at Battersea power station in London.
The main buildings of the South station had a total length of and a width of ; their tallest point, the roof of the boiler house, was high. The main buildings of the North station were of a similar length and height, but in total slightly narrower as the station had one less generator unit. This also meant it had a smaller generating capacity; it was sometimes erroneously termed the South station's "B" station.
The boiler houses and turbine halls were all-welded steel structures, consisting of box-type main columns and roof girders, clad with brick and glazed in parts. Each of their four chimneys was made of brick and stood tall, weighing about 5,000 tonnes. The North station's four cooling towers were made from reinforced concrete and were of the typically hyperbolic, :File:Stella cooling towers.jpg|natural-draft design.
The South station had five generating sets and the North station had four. Each generating set had a bunker for 1,250 tonnes of coal, fed by a conveyor from the coal store. This conveyor belt system was built by E. N. Mackley & Co, Gateshead. Each bunker fed coal into a pulveriser, manufactured by Raymond. From here it was fed into a boiler in powder form and burned. All of the boilers were suspended from the boiler houses' steel frames, and were made by Clarke Chapman Group Ltd, Gateshead. The boilers were forged in Sheffield, the first of the nine arriving at Stella South in 1953. At 62 tonnes, the boilers were at the time the largest ever made in the UK. The boilers were of the radiant-heat type, comprising a water-cooled combustion chamber, controlled-type superheater and an economiser. Each of the boilers had an evaporation rating of 550 kL/h, a steam pressure of 950 psi and a steam temperature of 925 °F. Each boiler was equipped with two forced and two induced Howden fans, twenty-two electrically operated Clyde soot blowers, an automatic control system made by Bailey and Sturtevant electrostatic precipitators. Each station was designed to burn 2,000 tonnes of bituminous coal a day.
Each boiler powered a turbo generator, made by Parsons, Newcastle upon Tyne. These were three-cylinder reaction type steam turbines operating at 3,000 rpm, generating 60 MW of electricity. The stations used them because of a Statutory Order of the Ministry of Supply in November 1947 that all turbo alternators made for the home market could only be of 60 MW at advanced steam conditions. Stella South had a total generating capacity of 300 MW and Stella North originally 240 MW. The stations were the first to use silica removal beds in their turbines, a development which became standard within the CEGB's power stations for some time. In 1967, one of the sets at Stella South became the world's first in commercial operation to use brushless excitation. The set was modified by Parsons to use A.C. exciters and silicon diode rectifiers. The stations' switchgear was manufactured by A. Reyrolle & Company.
The power stations were illuminated by what was then the most powerful lighting installation in North East England. The North station was lit up by 60 flood lights, 15 on each of four towers; the South station also had four towers, but each held 26 flood lights. The Central Electricity Authority justified the use of 194 flood lights over the two sites as "economical, safe and much more efficient than lighting the stations at street level".

Operations

Coal transportation

The stations were in the heart of the North East coal field, which at the time of their opening had hundreds of collieries. Coal was delivered straight to the stations by rail. The Newcastle and Carlisle Railway was used for the South station, where 22 railway sidings were built. Trains could only enter the sidings when travelling in a westerly direction.
The Scotswood, Newburn and Wylam Railway supplied the North station, trains reaching the power station via a junction at Newburn. Despite the SN&WR's closure on 11 March 1968, and the rerouting of the Newcastle & Carlisle Railway through Dunston in 1982, the track between Scotswood and Newburn was retained for supplying the North station, as well as for rail access to the neighbouring Ever Ready battery factory and Anglo Great Lakes Graphite Plant. The tracks outlived the power stations, and were finally lifted when the Ever Ready factory shut down in 1992. Part of the line serving the station is now a well-used section of the Hadrian's Way National Trail.
A small home fleet of locomotives was used to shunt the coal wagons once they had arrived at the stations. Originally this included Robert Stephenson and Hawthorns 0-4-0ST No.20 and No.21, and Sentinel No.25. Engine No.25 was used exclusively at the North station, but was converted to diesel-hydraulic by Thomas Hill of Kilnhurst in 1967, becoming Thomas Hill 188. It returned to the station but was taken out of use in 1983 and scrapped by C F Booth of Rotherham. After the closure of the stations, engine No.21 was sent to be preserved at the Tanfield Railway site, near Sunniside in Gateshead. During the 1970s the steam locomotives were replaced by diesel locomotives. These included a Fowler 0-6-0 and CEGB No. 24 Vanguard 0-4-0 CEGB No. 24 has since been sent to Statfold Barn Railway for preservation.
The stations were picketed during the UK miners' strike of 1972, stopping coal deliveries to them.

Cooling system

Water is essential to a thermal power station to produce the steam needed to turn the steam turbines and generate electricity. Water cycled through the Stella stations' systems was taken from the River Tyne; after use it was cooled before being discharged back into the river. The North station's water cooling system consisted of four large natural draft cooling tower units, tall and made of reinforced concrete. The South station used a syphon cooling system instead of cooling towers, consisting of five units, made up of five underground pipes, each in diameter, with valves and screens.

Ash removal

and bottom ash are two by-products from the burning of coal in power stations. Ash from the Stella stations was taken out to sea by three flat iron barges: Bobby Shaftoe, Bessie Surtees and Hexhamshire Lass. All three were built by Charles Hill & Sons of Bristol, in 1955. Bessie Surtees was the first to be put into service, in April 1955. On each trip, each ship took up to 500 tonnes of ash from the stations down the river and dumped it in the North Sea, off the coast. Originally, they carried ash waste from Dunston power station as well. Their frequent passages made them a common sight on the Tyne. Each was long and wide, weighed 680 tonnes, and had a crew of seven. They were managed by Stephenson Clarke Shipping Ltd but owned by the CEGB. The ships went further up the Tyne than did any other, and so needed a shallow draft. The entire load of ash was dumped through two hydraulically operated doors in only a few minutes.
As early as the 1960s, the power stations' operating hours were decreased due to the opening of the much larger Blyth power station in Northumberland. This meant that less ash was produced by the Stella and Dunston stations; so by the end of the 1960s, the CEGB sold Hexhamshire Lass and Bobby Shaftoe. The former went to a firm in Fareham, Hampshire, where it worked as a sand dredger until scrapped in 1993; the latter to a French dredging company.
After the closure of Dunston Staithes in 1980, the Swing Bridge downstream of the stations seldom had to be opened. However, on 15 December 1975, Bessie Surtees collided with the Swing Bridge, forcing it to close for the rest of that weekend.

Environmental impact

When built, the power stations were fitted with electrostatic precipitators, to reduce the amount of smoke and dust emitted from the stations' chimneys. At the time, this was the most up-to-date method to prevent pollution from power stations.
Despite these precautions, pollution from the power stations was still a factor. In 1954, consideration was given to scrapping the plan to build the Union Hall housing estate in Lemington because of probable pollution from nearby power stations. This was mainly because some of the houses were as high as, if not higher than, the power stations' chimneys. At times, this meant the estate being exposed to as much as 1.25 parts per million of sulphur dioxide. However the estate was still built, as these peak conditions were thought unlikely to occur on more than 18 days in a year.
Smoke was not the only thing emitted from the power station. In July 1956, the discharge of cooling water from the stations was noted to have increased the water temperature of the river by 1.5 °C between Ryton and Scotswood. However, this was found to not be too deleterious, as it did not seem to affect the passage of migratory fish. In fact, because of the stations' introduction of warm water into the river, basking sharks were known to be attracted to the area.
From the start, the power stations' fly ash was dumped in the North Sea, and 800,000 tonnes of fly ash were dumped between the Stella and Blyth stations in 1976. By 1991, National Power's licence had been restricted to dumping only 50,000 tonnes of ash a year from the Stella power stations. By this point the North East coast was the only place in Europe to dump fly ash at sea. Fly ash dumping had been found to make sea bed inert, with much life being smothered and killed by the fly ash. It was also found to create problems for the fishing industry, when their trawlers caught large lumps of it. The licence for Stella was terminated in May 1991, with the stations' closure. Blyth power stations' licence was terminated by the end of 1992, ending fly ash dumping in the North Sea.

Closure and demolition

Closure

By the mid-1980s closure of the stations was being considered, and in 1984, was considered for a combined heat and power scheme. After the privatisation of the Central Electricity Generating Board in 1989, the stations passed into the ownership of National Power. After almost 37 years of use they were decommissioned in May 1991 as outdated and uneconomical to operate. They had been overtaken technologically, and had lower generating capacity than newer plants such as Drax. Their closure coincided with that of a large number of coal mines in the North East of England, just after the privatisation of both the electricity industry and the National Coal Board in the early 1990s.
Following the closure of the power stations at Stella, as well as those at Dunston and Blyth, the northern part of North East England has become heavily dependent upon the National Grid for electricity. However, in the South of the region there are still two large power stations, at Hartlepool and Wilton.
The stations' closure also forced the Tyne Sea Scouts, who had operated from the North station since 1978, to seek new accommodation. The scouts had moved into the station when their boat house in Blyth was deemed unsafe and demolished. They had been provided with two site offices, storage in the power station complex, and permission to keep their boats at the North station's jetty, at the end of which they had a slipway built.

Demolition

The large buildings and structures of the stations were demolished in stages throughout the 1990s. The four cooling towers were demolished by explosives on 29 March 1992, in front of thousands of spectators. St Paul's Developments then bought the two sites from National Power in 1993. Both stations were demolished by Thos W Ward Industrial Dismantling of Barnsley, which started with the South station, whose twin chimneys were destroyed on 29 October 1995 by of explosives. Its turbine hall followed, before the boiler house went on 1 February 1996. Stella North then stood alone for almost a year before its turbine hall was demolished on 27 January 1997 and its bunker bay building was demolished on 22 June. The boiler house followed straight after, but its complete destruction took three attempts. Most of it went on 22 June; the rest followed over the next two days. Its two chimneys, the last obvious reminder of the Stella power stations, were pulled down a month later on 27 July.
The power stations were among the last remaining heavy industrial buildings in modern Tyneside, and their demolition was felt by many Tynesiders to have marked the end of industrial Tyneside. The National Trust was then uninterested in the preservation of modern structures such as this.

Redevelopment

North site

CCGT power station proposal

In 1997 there had been plans for a £130 million combined cycle gas turbine power station on the site of the Ever Ready battery factory to the West of the site of the North station. AES Electrical applied to the Department of Trade and Industry for permission to build the station, which would have been twice as efficient as the coal-fired Stella stations and the first major electricity generation site built in Tyne and Wear in over 40 years. The station would have had a generating capacity of 350 MW. It would have taken three years to build, and created 400 construction jobs, as well as 40 full-time jobs after construction. But the proposal was opposed by the coal mining industry and dropped.

Newburn Riverside

Shortly after the North station was demolished, its site was reclaimed along with the site of the neighbouring Anglo Great Lakes Graphite Plant. The plant had made high-purity graphite for use in magnox nuclear reactors, and operated using the North station's available excess generating capacity, as large quantities of cheap electricity were essential for production. It was demolished around the same time as the stations, and left the site littered with graphite blocks. At, the reclamation of the two neighbouring sites was one of the UK's largest land reclamation schemes; it was completed in 2000. This made way for an industrial/business park, Newburn Riverside, the first phase of whose construction was completed in 2005. As of 2009 it was still expanding, and expected to provide 5,000 jobs and £116 million of private sector investment once completed. The park has a cycle route and nature trail around its edge, which takes visitors, walkers and cyclists beside the river and past the point in which the North station's cooling towers once stood. One of the buildings in the business park was named Stella House, as a tribute to the power station. It is occupied by One NorthEast, the regional development agency for the North East of England. In early 2012, Stella House became the National HQ of the NHS Business Service Authority following the winding down of One NorthEast. Little else commemorates the power stations, but they are briefly mentioned in a plaque on Stella Road near the South station's site marking the Blaydon Races: "Official racing started in 1861 on Blaydon Island which lay North of here. The song was written in 1862. From 1887 to 1914 the race course was on Stella haugh, the site of the former power station."
As well as the NHSBSA, the other key occupiers of the Newburn Riverside site are DEFRA, North East Ambulance Trust, MacFarlane Packaging, True Potential LLP, Northumberland and Tyne & Wear Strategic Health Authority and Stannah Stairlifts.

South site

Following the completion of the South station's demolition in 1996, thousands of pounds were spent on a number of security measures; the site was fenced off, bunding was installed, warning signs were put up and security patrols took place. However, large sections of the fencing were stolen and the warning signs were ignored. Ultimately this led to one man being trapped on the site for five hours on 22 May 1997. He had been looking for scrap metal and power cables, and had climbed through a small hole into an underground room, from which he had to be rescued by fire crews. The site was then designated a danger zone. The derelict site was vandalised in July 1999, when people hurled burning tyres into the sub-station, creating a fire and damaging cables worth £150,000.

Riverside Crescent

As of 2007, the site of the South station is under redevelopment, after having sat as a brownfield site for almost 10 years. St Paul's Developments, the site developer, had often applied for planning permission to build housing and leisure facilities on the site over the course of six years, only to be refused. It was finally granted permission to begin building a £4.7 million housing estate on the site in 2007. Named Riverside Crescent, this is being constructed by Barratt and Persimmon. It will have 522 residential units, from two-bedroom flats to five-bedroom houses, as well as of open space, a riverside walkway and a restaurant. A new bus link to Blaydon will improve transport links. The plans for the residential development first went on display at Stella RC Primary School on 5 October 2005. Other proposals for the site had included industrial development, which met opposition, and restoration to grassland, seen as unfeasible.
Despite the demolition in 1996 of all of the above-ground structure of the South station, foundations, culverts and more remained. These needed to be removed before construction could start. The removal of these underground structures was completed in early 2007, whereupon construction of the houses began immediately.

Remnants

Due to the significant reclamation on the two sites very little evidence remains of the power stations, other than a small number of bricks and steel rods. Some minor structures have survived to the North West of the North station's site, including a road bridge over the rail line which served the station, a brick wall, and a concrete staircase. More obvious remains of the power stations are their three large sub-stations that still supply the local region. Much of that electrical power was generated in Scotland's Cockenzie power station, transported via a 275 kilovolt and a 400 kV connection.

Cultural use

The power stations were a strong local landmark. Their chimneys could be seen along a roughly long section of the Tyne valley; from Bensham near Gateshead down to Heddon-on-the-Wall in Northumberland: almost no other building was present to obstruct the view.
When still in operation, the power stations appeared in films and television programs shot in the Newcastle area. They appeared in Payroll, a movie made in 1961, starring Michael Craig. One of two security van operators lives in Stella park, a housing estate above the power station. It is prominently in the background whenever the van operator's home is shown. In 1985, the Stella power stations are seen briefly in a shot in Seacoal, a movie made by Amber Films. They appear during a scene where the two protagonists, Ray and Betty, are travelling from Sunderland to Newcastle. In Whatever Happened to the Likely Lads?, a British sitcom broadcast between 1973 and 1974, the stations themselves did not appear in the series, but in the end credits their ash boat, Bessie Surtees, could be seen passing Spiller's Wharf near Byker. In 1981, it was featured in Swing Bridge Videos' Check it Out, a short film about youth unemployment in the west end of Newcastle. In the mid-1990s, the decommissioned stations were photographed by north eastern artist John Kippin as part of his work The Secret Intelligence of the Silent. This piece was exhibited at the Laing Art Gallery in 2012 as part of the exhibition Futureland Now.