Ship-Submarine Recycling Program
The Ship/Submarine Recycling Program is the process that the United States Navy uses to dispose of decommissioned nuclear vessels. SRP takes place only at the Puget Sound Naval Shipyard in Bremerton, Washington, but the preparations can begin elsewhere.
Program overview
Defueling and decommissioning
Before SRP can begin, the vessel's nuclear fuel must be removed, and defueling usually coincides with decommissioning. Until the fuel is removed, the vessel is referred to as "USS Name," but afterward the "USS" is dropped and it is referred to as "ex-Name." Reusable equipment is removed at the same time as the fuel.Spent fuel storage
Spent nuclear fuel is shipped by rail to the Naval Reactor Facility in the Idaho National Laboratory, located northwest of Idaho Falls, Idaho, where it is stored in special canisters.Hull salvage
At PSNS the SRP proper begins. The salvage workers cut the submarine into three or four pieces: the aft section, the reactor compartment, the missile compartment if one exists, and the forward section. Missile compartments are dismantled according to the provisions of the Strategic Arms Reductions Treaty.Until 1991, the forward and aft sections of the submarines were rejoined and placed in floating storage. Various proposals for disposal of those hulls were considered, including sinking them at sea, but none was economically practical. Some submarines built prior to the 1978 banning of polychlorinated biphenyl products had the chemicals on board, which are considered hazardous materials by the Environmental Protection Agency and United States Coast Guard, requiring their removal. Since then, and to help reduce costs, the remaining submarine sections are recycled, returning reusable materials to production. In the process of submarine recycling, all hazardous and toxic wastes are identified and removed, reusable equipment is removed and put into inventory. Scrap metals and all other materials are sold to private companies or reused. The overall process is not profitable, but does provide some cost relief. Disposal of submarines by the SRP costs the Navy US$25–50 million per submarine.
Reactor vessel disposal
Once the de-fueled reactor compartment is removed, it is sealed at both ends and shipped by barge and multiple-wheel high-capacity trailers to the Department of Energy's Hanford Nuclear Reservation in Washington state, where they are currently,, kept in open dry storage and slated to be eventually buried. Russian submarine reactor compartments are stored in similar fashion near Murmansk.The burial trenches have been evaluated to be secure for at least 600 years before the first pinhole penetration of some lead containment areas of the reactor compartment packages occurs, and several thousand years before leakage becomes possible.Prior disposal methods
In 1959 the US Navy removed a nuclear reactor from the submarine and replaced it with a new type. The removed reactor was scuttled in the Atlantic Ocean, east of Delaware, at a depth of.In 1972, the London Dumping Convention restricted ocean disposal of radioactive waste and in 1993, ocean disposal of radioactive waste was completely banned. The US Navy began a study on scrapping nuclear submarines; two years later shallow land burial of reactor compartments was selected as the most suitable option.
In 1990, was the first US nuclear-powered submarine to be scrapped.
Future salvage work
By the end of 2005, 195 nuclear submarines had been ordered or built in the US. The last of the regular attack boats,, was decommissioned in 2001, and, a highly modified Sturgeon, was decommissioned in 2004. The last of the initial "41 for Freedom" fleet ballistic missile submarines,, was decommissioned in 2002. Decommissioning of the boats began in 1995 with. Additionally, a handful of nuclear-powered cruisers have entered the program, and their dismantling is ongoing. The first aircraft carrier due for decommissioning that would enter the SRP is planned to be, which was withdrawn in 2013. Hulls waiting or already processed by the recycling program are listed below.Lists of vessels by type
Cruisers
† A dagger after a completion date indicates that portions of the hull were preserved as memorials. See the individual articles for details.ex-Long Beach has been partially dismantled and remains moored in Puget Sound Naval Shipyard in 2018.
Attack submarines
Some of these submarines were fleet ballistic missile boats for the vast majority of their careers. However, they were briefly converted to SSNs before decommissioning and arrival at PSNS, and so are listed under that designation here.Ship name | Start date | Completion date/status |
ex-Seawolf | 1 October 1996 | 30 September 1997 |
ex-Skate | 14 April 1994 | 6 March 1995 |
ex-Swordfish | Unknown | 11 September 1995 |
ex-Sargo | 14 April 1994 | 5 April 1995 |
ex-Seadragon | 1 October 1994 | 18 September 1995 |
ex-Skipjack | 17 March 1996 | 1 September 1998 |
ex-Triton | 1 October 2007 | 30 November 2009 |
ex-Halibut | 12 July 1993 | 9 September 1994 |
ex-Scamp | 1990 | 9 September 1994 |
ex-Sculpin | 1 October 2000 | 30 October 2001 |
ex-Shark | 1 October 1995 | 28 June 1996 |
ex-Snook | 1 October 1996 | 30 June 1997 |
ex-Permit | 30 September 1991 | 20 May 1993 |
ex-Plunger | 5 January 1995 | 8 March 1996 |
ex-Barb | Unknown | 14 March 1996 |
ex-Tullibee | 5 January 1995 | 1 April 1996 |
ex-George Washington | Unknown | 30 September 1998† |
ex-Patrick Henry | 1 October 1996 | 31 August 1997 |
ex-Robert E. Lee | Unknown | 30 September 1991 |
ex-Pollack | 9 February 1993 | 17 February 1995 |
ex-Haddo | Unknown | 30 June 1992 |
ex-Jack | Unknown | 30 June 1992 |
ex-Tinosa | 15 July 1991 | 26 June 1992 |
ex-Dace | Unknown | 1 January 1997 |
ex-Ethan Allen | Unknown | 30 July 1999 |
ex-Sam Houston | 1 March 1991 | 3 February 1992 |
ex-Thomas A. Edison | 1 October 1996 | 1 December 1997 |
ex-John Marshall | 22 July 1992 | 29 March 1993 |
ex-Guardfish | Unknown | 9 July 1992 |
ex-Flasher | Unknown | 11 May 1994 |
ex-Greenling | 30 September 1993 | 18 April 1994 |
ex-Gato | Unknown | 1 November 1996 |
ex-Haddock | 1 October 2000 | 1 October 2001 |
ex-Sturgeon | Unknown | 11 December 1995 † |
ex-Whale | 20 October 1995 | 1 July 1996 |
ex-Tautog | 15 March 2003 | 30 September 2004 |
ex-Kamehameha | 1 October 2001 | 28 February 2003 |
ex-James K. Polk | 16 February 1999 | 15 July 2000 |
ex-Grayling | 18 July 1997 | 31 March 1998 |
ex-Pogy | 4 January 1999 | 12 April 2000 |
ex-Aspro | 1 October 1999 | 3 November 2000 |
ex-Sunfish | Unknown | 31 October 1997 |
ex-Pargo | 1 October 1994 | 15 October 1996 |
ex-Queenfish | 1 May 1992 | 7 April 1993 |
ex-Puffer | 20 October 1995 | 12 July 1996 |
ex-Ray | 15 March 2002 | 30 July 2003 |
ex-Sand Lance | 1 April 1998 | 30 August 1999 |
ex-Lapon | 15 March 2003 | 30 November 2004 |
ex-Gurnard | Unknown | 15 October 1996 |
ex-Hammerhead | Unknown | 22 November 1995 |
ex-Sea Devil | 1 March 1998 | 7 September 1999 |
ex-Guitarro | Unknown | 18 October 1994 |
ex-Hawkbill | 1 October 1999 | 1 December 2000 † |
ex-Bergall | Unknown | 29 September 1997 |
Ship name | Start date | Completion date/status |
ex-Spadefish | 1 October 1996 | 24 October 1997 |
ex-Seahorse | 1 March 1995 | 30 September 1996 |
ex-Finback | Unknown | 30 October 1997 |
ex-Narwhal | 1 October 2001 | |
ex-Pintado | 1 October 1997 | 27 October 1998 |
ex-Flying Fish | Unknown | 15 October 1996 |
ex-Trepang | 4 January 1999 | 7 April 2000 |
ex-Bluefish | 15 March 2002 | 1 November 2003 |
ex-Billfish | Unknown | 26 April 2000 |
ex-Drum | 1 December 2008 | 20 May 2010 |
ex-Archerfish | Unknown | 6 November 1998 |
ex-Silversides | 1 October 2000 | 1 October 2001 |
ex-William H. Bates | 1 October 2002 | 30 October 2002 |
ex-Batfish | Unknown | 22 November 2002 |
ex-Tunny | 1 October 1997 | 27 October 1998 |
ex-Parche | 30 September 2004‡ | 30 November 2006 |
ex-Cavalla | 1 October 1999 | 16 November 2000 |
ex-Glenard P. Lipscomb | Unknown | 1 December 1997 |
ex-L. Mendel Rivers | 29 November 2000 | 19 July 2002 |
ex-Richard B. Russell | 1 October 2001 | 19 September 2002 |
ex-Los Angeles | February 2011 | 5 March 2013 |
ex-Baton Rouge | 13 January 1995 | 30 September 1997 |
ex-Philadelphia | 1 September 2019 | De-fueled, inactivated |
ex-Memphis | 14 December 2010 | De-fueled, inactivated |
ex-Omaha | 1 October 2009 | 7 November 2011 |
ex-Cincinnati | 1 October 2009 | 22 September 2014 |
ex-Groton | 1 June 2012 | 5 May 2014 |
ex-Birmingham | 1 June 2012 | 23 September 2015 |
ex-New York City | 1 June 2011 | Decommissioned 30 April 1997 |
ex-Indianapolis | 1 October 2013 | Recycling begun |
ex-Bremerton | 13 February 2014 | Still operational as of 23 May 2017 |
ex-Jacksonville | 31 March 2014 | Still operational as of 23 May 2017 |
ex-Dallas | 22 May 2017 | Arrived PSNS 22 May 2017 |
ex-La Jolla | refit | n/a |
ex-Phoenix | 1 June 2013 | 20 September 2016 |
ex-Boston | 1 October 2001 | 19 September 2002 † |
ex-Baltimore | 1 June 2013 | Decommissioned 10 July 1998 |
ex-City of Corpus Christi | 24 November 2015 | Being de-fueled/inactivated |
ex-Albuquerque | 14 April 2016 | De-fueled, inactivated |
ex-Portsmouth | 1 June 2015 | De-fueled, inactivated |
ex-Minneapolis-St. Paul | 1 June 2018 | De-fueled, inactivated |
ex-Hyman G. Rickover | 30 September 2016 | De-fueled, inactivated |
ex-Augusta | 1 September 2019 | De-fueled, inactivated |
ex-San Francisco | refit | n/a |
ex-Atlanta | 1 October 2013 | Recycling begun |
ex-Houston | 21 September 2015 | Being de-fueled/inactivated |
ex-Norfolk | 11 December 2014 | De-fueled, inactivated |
ex-Buffalo | 26 May 2017 | Arrived PSNS 26 May 2017 |
ex-Salt Lake City | 30 September 2015 | De-fueled, inactivated |
ex-Honolulu | 1 November 2006 | 20 October 2008 |
ex-Miami | 28 March 2014 | De-fueled, inactivated |
Ship name | Start date | Completion date/status |
† A dagger after a completion date indicates that portions of the hull were preserved as memorials. See the individual articles for details.
‡ Date given for ex-Parche is official date used to secure FY2004 funding; work did not begin until 19 October.
La Jolla is currently undergoing conversion to a moored training ship at Norfolk Naval Shipyard. San Francisco will be converted after decommissioning.
Ballistic missile submarines
Some of these submarines were fleet ballistic missile boats for the vast majority of their careers. However, they were converted to SSNs for use as moored training platforms and are not currently scheduled for recycling.Ship name | Start date | Completion date |
See Attack Submarines – | n/a | n/a |
See Attack Submarines – | n/a | n/a |
ex-Theodore Roosevelt | unknown | 24 March 1995 |
See Attack Submarines – | n/a | n/a |
ex-Abraham Lincoln | unknown | 5 May 1994 |
See Attack Submarines – | n/a | n/a |
See Attack Submarines – | n/a | n/a |
See Attack Submarines – | n/a | n/a |
See Attack Submarines – | n/a | n/a |
ex-Lafayette | 1 March 1991 | 25 February 1992 |
ex-Alexander Hamilton | 23 February 1993 | 28 February 1994 |
ex-Thomas Jefferson | 1 October 1996 | 6 March 1998† |
ex-Andrew Jackson | unknown | 30 August 1999 |
ex-John Adams | unknown | 12 February 1996 |
ex-James Monroe | unknown | 10 January 1995 |
ex-Nathan Hale | 2 October 1991 | 5 April 1995 |
ex-Woodrow Wilson | 26 September 1997 | 27 October 1998† |
ex-Henry Clay | unknown | 30 September 1997 |
ex-Daniel Webster | refit | n/a |
ex-James Madison | unknown | 24 October 1997 |
ex-Tecumseh | 15 February 1993 | 1 April 1994 |
ex-Daniel Boone | unknown | 4 November 1994 |
ex-John C. Calhoun | unknown | 18 November 1994 |
ex-Ulysses S. Grant | unknown | 23 October 1993 |
ex-Von Steuben | 1 October 2000 | 30 October 2001 |
ex-Casimir Pulaski | unknown | 21 October 1994 |
ex-Stonewall Jackson | unknown | 13 October 1995 |
ex-Sam Rayburn | refit | n/a |
ex-Nathanael Greene | 1 September 1998 | 20 October 2000 |
ex-Benjamin Franklin | unknown | 21 August 1995 |
ex-Simon Bolivar | 1 October 1994 | 1 December 1995 |
ex-George Bancroft | unknown | 30 March 1998† |
ex-Lewis and Clark | 1 October 1995 | 23 September 1996 |
ex-George C. Marshall | unknown | 28 February 1994 |
ex-Henry L. Stimson | unknown | 12 August 1994 |
ex-George Washington Carver | unknown | 21 March 1994 |
ex-Francis Scott Key | unknown | 1 September 1995 |
ex-Mariano G. Vallejo | 1 October 1994 | 22 December 1995 |
ex-Will Rogers | 12 April 1993 | 12 August 1994 |
† A dagger after a completion date indicates that portions of the hull were preserved as memorials. See the individual articles for details.
Because the program is underway, this list is almost certainly incomplete.
Note for ships marked with refit:
Sam Rayburn was converted into a training platform - Moored Training Ship. Sam Rayburn arrived for conversion on 1 February 1986, and on 29 July 1989 the first moored training ship achieved initial criticality. Modifications included special mooring arrangements including a mechanism to absorb power generated by the main propulsion shaft. Daniel Webster was converted to the second Moored Training Ship in 1993. The Moored Training Ship Site is located at Naval Weapons Station Charleston in Goose Creek, South Carolina. Sam Rayburn is scheduled to operate as an MTS until 2014 while undergoing shipyard availabilities at four-year intervals.