Mitsubishi SpaceJet


The Mitsubishi SpaceJet, formerly known as the Mitsubishi Regional Jet, or MRJ for short, is a twin-engine regional jet aircraft seating 70–90 passengers manufactured by Mitsubishi Aircraft Corporation, a partnership between majority owner Mitsubishi Heavy Industries and minority owner Toyota Motor Corporation with design assistance from Subaru Corporation, itself already an aerospace manufacturer. The SpaceJet will be the first airliner designed and produced in Japan since the NAMC YS-11 of the 1960s, which was produced at a loss.
The first flight of the MRJ was in November 2015. After several delays, deliveries were scheduled to start by mid-2020, later delayed again in late 2021 or in 2022.

Development

Launch

In 2003 the Japanese government started a five-year, ¥50 billion research program to study an indigenous regional jet for 30 to 90 passengers, led by Mitsubishi Heavy Industries.
In 2004 MHI was focused on a 2m high by 2.8m-wide, four-seat-abreast cabin, seating 30 to 50 passengers, and was hoping to fly a prototype in 2007 and deliver the first aircraft in 2010.
In 2005 it switched to a larger 70-90 seat category.
MHI launched its concept at the 47th Paris Air Show in June 2007, showing a full-scale cabin mock-up and aiming to be the first regional jet all-composite airframe, with certification targeted for 2012.
Mitsubishi formally offered the MRJ to airlines in October 2007 - the first Japanese airliner since the NAMC YS-11 production stopped in 1974 - after being the first airframer to select the Pratt & Whitney PW1000G geared turbofan offering a 12% reduction in thrust specific fuel consumption, rated at thrust on the 70- to 80-seat MRJ70 and 17,000 lb thrust on the 86- to 96-seat MRJ90, projecting a ¥150 billion development cost.
MHI officially launched the Mitsubishi Regional Jet Program on March 28, 2008 with an order for 25 aircraft from All Nippon Airways, targeting a 2013 introduction.
Mitsubishi is targeting a 20% share of 5,000 sales forecast in the 70-90-seat bracket over 20 years.
Flight testing was scheduled for late 2011 and the $1.9-billion programme necessitates 300-400 sales to recoup its cost.

Design

In September 2009 Mitsubishi unveiled extensive design changes, using aluminium instead of carbon fibre composites for the aircraft's wings and wingbox; the remaining composite parts will make up 10-15% of the airframe: the empennage.
The cabin height is increased by to and the fuselage height is increased to, giving a rounder cabin, wider and higher than its competition.
The program was delayed six months with final design frozen in mid-2010, first flight delayed to the second quarter of 2012 and deliveries to early 2014.
Maintenance intervals are 750 flight hours per A Check and 7,500 flight hours per C check.
A 100-seat stretched MRJ100 was studied in March 2011. it was still under evaluation.
As the MRJ90 MTOW of 39.6 t is above the US regional carriers scope clause of 39 t, SkyWest and Trans States Holdings could convert their MRJ90 orders for 100 and 50, respectively, to the 1.4 m shorter MRJ70: 67% of the 223 firm MRJ90 orders.
But the MRJ70 seats only 69 in two classes and attain the 76 seats scope close limit only in all-economy: Mitsubishi wants to increase seating within its fuselage to compete with the currently compliant Embraer E-175 and Bombardier CRJ900.
Mitsubishi is working on a three-class, 76-seat design, with more premium seating than the MRJ70 but still within the scope-clause MTOW, to be unveiled at the June 2019 Paris Air Show.
The reworked MRJ70 will be called the Space Jet M100, its type certificate is expected in 2022 and Mitsubishi considers U.S. production. Program cost is expected to reach ¥800 billion by the 2020 debut of the SpaceJet M90.

Assembly

On 15 September 2010, the Mitsubishi Aircraft Corporation announced that it had entered the production drawing phase and was proceeding with the manufacturing process.
Assembly of the first aircraft began in April 2011 with construction of the emergency escape for the cockpit.
In April 2012, first flight was delayed to 2013.
In December 2012, the MRJ90s delivery was scheduled for 2017.
In early 2013, Pratt & Whitney delayed the PW1200G certification to the "latter half" of 2014, after the MRJ first flight scheduled for late 2013.
On 22 August 2013, Mitsubishi announced a third delay to the program, and that the first flight would take place in the second quarter of 2015 instead of end-2013, while the first delivery to launch customer ANA would take place in the second quarter of 2017 instead of 2015, due to parts delivery problems including Pratt & Whitney engines.
On 7 September 2013 were exhibited a prototype of the left wing and four aluminium sections : forward fuselage, front mid fuselage, aft mid fuselage and aft fuselage, to be assembled in October 2013.
Mitsubishi has hired foreign experts to help with relations with suppliers, ground tests, flight tests, and certification.
Pictures of the first fully assembled MRJ90 were available on 26 June 2014.
An official rollout occurred on 18 October 2014.

Testing

The maiden flight of the MRJ90 took place on 11 November 2015. On 24 December, Mitsubishi announced a one-year delay for the first delivery of the MRJ, to mid-2018. The delay was attributed to insufficient wing strength and the redesign of the landing gear for better safety.
Much of the flight testing for the MRJ90 will take place in Moses Lake, Washington, at the Grant County International Airport, due to the crowded airspace in Japan causing scheduling difficulties. Static strength tests were completed on November 1, 2016 and confirmed that the airframe could withstand 1.5 times the maximum load.
In January 2017, a further two-year delay was announced, pushing the expected first delivery to mid 2020. This resulted from moving the avionics bay and wiring looms and in March the flight certification program was extended from 2500 to 3000 flying hours. Mitsubishi didn't confirm. Four of the five delays were caused, at least partly, by failures to document work for certification or similar failures. As a result, development cost ballooned to 350 billion yen and the project might never able to fully recover its costs. Mitsubishi originally planned to use five flight test aircraft and two ground test aircraft but one or two additional aircraft will also be needed following this introduction of a two-year delay to mid-2020.
Seattle engineering consultants Aerotec L.L.C. saw problems for avionics and its wiring certification: damage could cause single point of failure, due to fire, water flooding from a ruptured waterline, or from part penetration of an engine explosion. This necessitated hardware changes in the bays, now frozen, but the electrical wiring interconnection system had to be reconfigured with hired specialist Latecoere. In June 2017, 940 hours of flight tests have been done and the four prototypes have an above 98% availability. On 21 August, FTA-2 experienced a flameout west of Portland International where it landed; partial damage was confirmed in the PW1200G and the test fleet was grounded until the cause is known. Flight testing resumed on 6 September.
By December 2017, the MRJ test campaign was half done with 1,500 flight hours and less than 1% cancelled due to technical issues. Their rate is accelerating with tests set up before the January 2017 avionics bay redesign: special runway tests, extreme environment and high altitude tests, to be completed in 2018. An additional flight test aircraft incorporating the redesign will join the campaign in the second half of 2018, focused on wiring tests like lightning and high-intensity radio-frequency. Two additional aircraft, recently painted white and under structural assembly in December, will be completed and will join the flight test campaign towards the end of 2018. At the end of the year, the mid-2020 deadline seemed difficult to achieve.
In January 2018, the avionics bay rearrangement and rerouted wiring were almost complete to be adequate for extreme events such as bomb explosions or water ingress underfloor. Upgrades and ground tests were performed on four flight test aircraft from February to March at Moses Lake, preceding flight testing for natural icing, avionics and autopilot, performance, stability and control.
In April 2018, the test fleet had logged 1,900 flight hours.
The flight-test fleet attained 2,000 hours in May 2018, and as most of the flight envelope was explored, the next trimester shifted to runway performance: takeoff, landing and minimum control speeds. The MRJ70 test aircraft were in final assembly as of May for expected delivery by the end of 2021, one year after the MRJ90 introduction.
An MRJ in All Nippon Airways livery was exhibited at the July Farnborough Airshow, alongside appearances by the similar Embraer 190 E2 and larger Airbus A220.
In October 2018, Bombardier sued Mitsubishi in Seattle, alleging that its ex-employees stole trade secrets to help for US certification. By then, the four MRJ90 prototypes had clocked 2,400 hours, targeting certification in late 2019 or early 2020 and first delivery in mid-2020, while the smaller MRJ70 should be introduced in 2022. After the MRJ programme lost Y47.2 billion for six months to 30 September 2018 on top of its Y110 billion deficit, Mitsubishi Heavy Industries injected Y220bn in Mitsubishi Aircraft, raising its stake from 64% to 86.7% and capital from Y100 billion to Y270 billion. Mitsubishi wants to dismiss the Bombardier allegations and should be heard in Seattle's US District Court on 11 January 2019. By December 2018, the Japan Civil Aviation Bureau delivered its type inspection authorisation, allowing to debut certification flight testing in early 2019 with the four MRJ90 in Moses Lake.
In April 2019, a federal judge dismissed Bombardier's claims against Mitsubishi, a strong case but falling short as there was no proof that Mitsubishi knew about those secrets. By then, the program had completed 2,600 flight hours and was undergoing crosswind and climate testing, while two more MRJ90s should join this summer.
On 24 June 2019, Bombardier and Mitsubishi announced that Mitsubishi would purchase the CRJ Programme from Bombardier for US$550 million and assume US$200 million in liabilities. With the deal, Mitsubishi will acquire the maintenance, support, refurbishment, marketing, and sales activities for the CRJ Series aircraft, including the support network locations in Montréal, Québec and Toronto, Ontario, its service centres located in Bridgeport, West Virginia, and Tucson, Arizona, and the type certificates.

SpaceJet rename

In June 2019, Mitsubishi rebranded the MRJ program as the SpaceJet. The MRJ90 was renamed as the SpaceJet M90 and a 76-seat variant specially targeted to meet US scope clauses, to be known as the SpaceJet M100, was announced. This version will be longer than the abandoned MRJ70 but shorter than the M90.
The E175-E2 is heavier than the current, scope-compliant E175, with its larger GTF engines, and being longer and wider : when its cabin is full, it can only fill of fuel within the MTOW limit, limiting its range to a short.
Compared to the E175-E2, the M100 cabin is a tighter fit around its 76 seats, and its wing is lighter, having less span and with smaller winglets than the MRJ90, giving it 50% more fuel than the E175-E2 at the MTOW limit for a range with 76 passengers. Without the scope clause limit, a MTOW M100 could fly with 84 passengers.
The M100 redesign pushes back its service entry to 2023, one year later than the MRJ70, while the M90 will evolve into the M200.
The longer fuselage can seat 88 in single-class, and at, the wingspan is shorter with the modified canted wingtip.
The shorter span will allow operating at Colorado's Aspen/Pitkin County Airport, a popular tourist destination, the only in-production jet with the capability after the CRJ700 production ends.
MITAC partner Triumph Group's structural optimization should remove 15% of the combined structural weight of the wing, aft fuselage, and empennage.
Deliveries should begin in 2024.
The M90 in its final configuration first flew on 18 March 2020, before joining the rest of the test fleet in Moses Lake.
In May 2020, Mitsubishi halved the budget of the SpaceJet programme for the year ending 31 March 2021. It confirmed its commitment to the baseline M90 version but is to reconsider the M100 in the light of the impact of the COVID-19 pandemic on the aviation industry. All work on the SpaceJet outside Japan, including flight testing of the M90 at Moses Lake, will be repatriated to the company's headquarters in Nagoya.

Production

A new production facility for the aircraft was built at Komaki Airport in Nagoya, Japan, on land purchased from the government at a total cost of 60 billion yen. The 2015 roll-out of the MRJ took place at Komaki, which had previously been the development site of the Mitsubishi A6M Zero fighter.
Mitsubishi announced in June 2013 that it would establish a quality control facility in Illinois for the sourcing of MRJ components from the United States.
MHI employs new production methods such as integral wing stringers, unusually tight tolerances, shot peening of curved surfaces, and vacuum assisted resin transfer molding, intended to increase quality and thus reduce expensive fault correction to keep price competitive.
On 26 April 2017, the fifth MRJ was complete in ANA livery, lacking only engines and nose cone, aircraft number six and seven had their fuselage and wings joined without the tails and the eighth, the first MRJ70, was at the assembly line start; Mitsubishi can manufacture 12 aircraft concurrently: in station one are joined fuselage sections, in station two the landing gear, wings and horizontal stabilisers are attached, in section three the major components are assembled, in outfitting takes place in section four and ground tests in station five, then the completed aircraft moves to painting.

Specifications

Customers

The MRJ's future was uncertain after six years of delays, with 70% of the backlog shared by two US regional carriers bound by scope clauses: the MRJ90 is too heavy and the smaller MRJ70 accommodates seven seats less than the 76 permitted. Following five postponements, and having lost ten percent of the MRJ's order book following the acquisition of Eastern Air Lines by Swift Air, Mitsubishi Aircraft closed its books at the end of March 2018 with a negative net worth of $979 million.

Orders

was the first customer, with an order for 15 MRJ 90s and an option for 10 more.
At the July 2012 Farnborough Airshow, SkyWest agreed to buy 100 MRJ90s, to be delivered between 2017 and 2020. The deal is worth $4.2bn at list prices. During the 2013 Regional Airlines Association conference, held in Montreal, Quebec, Canada, Mitsubishi announced that ANI Group Holdings, which firmed a MoU for 5 MRJ aircraft in June 2011, cancelled the deal, without giving further details.
By December 2018, the MRJ90 had 213 firm orders plus 194 commitments. During 2019, some of these orders were subsequently cancelled or converted to the new M100 variant, which had 115 commitments from US operators as of 31 October 2019.

Cancelled orders

On 21 May 2017, Iran cancelled its plans to buy Mitsubishi's Regional Jet from the Japanese company. Inability to set a delivery timeline for ordered aircraft and lack of testing were cited as their main reasons.
On 31 October 2019, Trans State Holdings, Inc. cancelled its order for 100 MRJ90s because the aircraft does not comply with US airlines' scope clauses.

Potential orders

In March 2008, and again in October 2008, Sankei Shimbun and Fuji Sankei Business I reported that the government of Japan would buy ten MRJs to serve as short-haul and small-field VIP transports, supplementing the existing Japanese Air Force One Boeing 747 aircraft. The government was still considering this option as of July 2013, with MRJs possibly supplementing new Boeing 777 long-haul VIP transports, according to the Nihon Keizai Shimbun.
On 20 July 2016, one of the officials at Iran's ministry of transportation announced Iran is buying 25 ATR airplanes for Iran Aseman Airlines and for further purchases Mitsubishi has showed interest in offering 20 MRJ planes.
On 19 June 2019, Mitsubishi signed a Memorandum of Understanding with an unnamed American customer for 15 of the new 76-seat SpaceJet M100 variant, to be delivered from 2024.
On 5 September 2019, US regional carrier Mesa Airlines signed a Memorandum of Understanding for up to 100 SpaceJet M100s, 50 of which are targeted as firm orders and 50 as purchase rights. Deliveries would begin in 2024.