Hungry Horse Dam


Hungry Horse Dam is an arch dam in the western United States, on the South Fork Flathead River in the Rocky Mountains of northwest Montana. It is located in Flathead National Forest in Flathead County, about south of the west entrance to Glacier National Park, southeast of Columbia Falls, and northeast of Kalispell. The Hungry Horse project, dam, and powerplant are operated by the U.S. Bureau of Reclamation. The entrance road leading to the dam is located in Hungry Horse.
The purposes of the Hungry Horse Project authorized by law are irrigation, flood control, navigation, streamflow regulation, hydroelectric generation, and other beneficial uses such as recreation. However, no irrigation facilities were built and the project has no irrigation obligations. Hydroelectric power generation and flood control are the primary purposes of the dam. The dam, reservoir, and surrounding area are used for recreation. However, the once great lower gorge lies submerged underneath.

Dimensions and statistics

At in height, the dam was the third largest and second highest concrete dam in the world at the time of its completion in 1953, with a volume of. The dam's spillway is the highest morning glory structure in the world. The spillway is controlled by a The surface elevation of the reservoir is above sea level.

History

Construction was authorized by the Act of June 5, 1944. In April 1948, Reclamation awarded the $43.4 million dam construction contract to Morrison Knudsen, General Construction Company, and Shea Company. The Guy F. Atkinson Company won the contract to divert the river during dam construction. Two timber companies, Wixson and Crowe and J. H. Trisdale, cleared seven thousand acres to make way for the reservoir. Construction officially began with a weekend of ceremonies in June 1948. In September 1949, workers poured the first concrete. The project eventually used 3 million cubic yards of concrete. Engineers adopted air-entrained concrete to reduce the effect of freeze-thaw cycles and to make the material more stable and workable. They also incorporated fly ash into the concrete mix. Hungry Horse was the first dam built with these innovations. The construction claimed the lives of 23 men.
Construction was completed on July 16, 1953. At a ceremony on October 1, 1953, President Harry S. Truman threw a switch to start power generation. The road across the dam opened to the public on November 2, 1953.

Hydroelectric power generation

The project contributes to hydroelectric power generation not only at Hungry Horse Dam, but by storing and releasing water for use by downriver hydroelectric dams on the Flathead, Clark Fork, Pend Oreille, and Columbia rivers. About a billion kilowatt–hours are generated annually at Hungry Horse Dam, while in an average year the release water will generate about 4.6 billion kilowatt–hours of power as it passes through the series of downstream powerplants.
Power generating facilities at Hungry Horse Dam are housed in a building constructed across the river channel at the downstream toe of the dam. The original design included four 71,250-kilowatt generators—a total of 285 megawatts installed capacity. The generator capacity was uprated in the 1990s to 107,000 kilowatts each for a total capacity of 428 megawatts.
Nearby and downstream, an aluminum production plant was constructed in the mid-1950s, northeast of Columbia Falls.