Greater Gabbard wind farm


Greater Gabbard is a 504 MW wind farm on sandbanks off the coast of Suffolk in England at a cost of £1.5 billion. Onshore construction activities commenced in early July 2008 at Sizewell. It was completed on 7 September 2012 with all of the Siemens SWT3.6–107 turbines connected.
A 336 MW extension of the project called Galloper Wind Farm was commissioned in April 2018.

History

The project was originally developed by Greater Gabbard Offshore Winds Limited which was a joint venture between Airtricity and Fluor. Airtricity was subsequently bought by Scottish and Southern Energy who have bought out Fluor's 50% stake for £40m which is expected to cost £1.3b. Fluor are now contracted to design, supply, installation and commissioning of the balance of the plant. Scottish and Southern sold a 50% stake to RWE, the owners of Npower, in November 2008 for £308m.
The project was given the go-ahead in May 2008 and work started in June. In July 2011 erection of the turbines was two-thirds complete, with all the pile foundations installed.
In October 2009 Seajacks Ltd delivered its 7,000 tonne Leviathan vessel to Fluor Ltd which sailed to Harwich to prepare the hook-up and commissioning of an in-field substation and then installation of the turbines. The first foundations were installed in autumn 2009 with the first of a total of 140 turbines installed in the spring 2010.
Electricity generation began on 29 December 2010 and construction was completed on 7 September 2012. During April 2014 to March 2015 the wind farm produced 1.7 TWh, corresponding to a capacity factor of 39%.
The wind farm can be seen from the Stena Line Harwich to Hook of Holland car & passenger ferry as it passes the turbines within a few kilometres.

Galloper extension

An extension of the project, called Galloper, was agreed in May 2013. The proposal was to add up to 140 turbines to the development, producing up to 504 MW of electricity. The wind farm was expected to be completed in 2017. The project was being developed in partnership by RWE Innogy and SSE.
In November 2013 the project capacity was reduced to 68 turbines producing 340 MW. In March 2014, SSE announced that it would be pulling out of the project. In October 2014 RWE Innogy announced that it too was abandoning the project, but in December the company revealed that it was still seeking potential investment partners.
In October 2015 RWE Innogy secured the financing of the project with three other investors each taking 25% of the project - Macquarie Capital, UK Green Investment Bank and Siemens Financial Services. Siemens Wind Power has been awarded the turbine supply contract to deliver 56 Siemens SWT-6.0-154 turbines.
At the September 2018 formal inauguration Galloper is officially 353 MW. It is owned by innogy SE, Siemens Financial Services, Sumitomo Corporation, ESB and a consortium managed by Green Investment Group and Macquarie Infrastructure and Real Assets. Innogy SE led development and construction of the windfarm and will operate it on behalf of the project partners.

Greater Gabbard specifications

On 12 November 2009, a man was killed and a woman injured after a chain broke and the two people were hit with pieces of the chain. Police responded to the incident, and an investigation was launched. The casualties were on board a tugboat, the Typhoon.
On 21 May 2010, a man died and another suffered serious injuries following an accident at Parkeston Quay, Harwich. A Siemens engineer from Norresundby, Denmark, died in the incident. A 43-year-old German national was taken to Addenbrooke's Hospital. The incident happened at about 7.50 am while loading a wind turbine blade on the vessel Seajack. Siemens and Fluor were ordered to pay £1 million for the incident.
In September 2013 remedial work was begun on the export cables close to shore as the cables were not buried sufficiently deeply. The work which was meant to take three weeks was only finished in September 2014. The work caused problems for local fishermen who asked the Greater Gabbard Offshore Wind Farm for a disruption payment. A spokesman for SSE denied that the work was responsible for the snagging of fishing nets.