Don Bridge


The Don Bridge is a motorway viaduct in South Yorkshire, England.

History

The line of the fifteen-mile Doncaster By-Pass Motorway was fixed in the spring of 1957.

Design

Each carriageway is carried on a separate structure. Each carriageway is supported by five riveted steel girders. There are 2,225 tons of structural steelwork.

Construction

Construction of the Doncaster bypass started on 22 June 1959. There were 28 bridges in the contract for the Doncaster bypass, including five railway bridges.
The fabrication of the steelwork for the bridge took place at the West Bromwich Works. The steel superstructure for the bridge was launched from one end of the bridge on an embankment. The steel fabrication was sprayed with zinc. The concrete and steel design is known as composite construction.
The concrete beams were made by Ferro Concrete and Stone Co. Ltd of Retford.
The bypass was built by a consortium including Holland, Hannen & Cubitts, on a £6 million contract.

Structure

The south side of the bridge is in Warmsworth, and the north side is in Sprotbrough and Cusworth. The bridge crosses the Trans Pennine Trail, which follows the river. It is situated around one mile north of junction 36.