CNP-300
The CNP-300 is a pressurized water nuclear reactor developed by the China National Nuclear Corporation.
It is China's first commercial nuclear reactor design.
The reactor has a thermal capacity of 999 MW and a gross electrical capacity of 325 MW, with a net output of about 300 MWe.
Development of the reactor began in the 1970s, based on a nuclear submarine reactor design.
The first CNP-300 unit started operations in Qinshan Nuclear Power Plant in 1991.
The CNP-300 was the first Chinese nuclear reactor to be exported, with the installation of the first unit at Chashma Nuclear Power Plant in Pakistan.
The unit began operation in 2000.
Another unit was completed in 2011 and other two reactors are under construction at the same plant.