21st-century modernisation of the Great Western main line


plans to spend £5 billion on modernising the Great Western main line, its South Wales branch and other associated lines. The modernisation plans were announced at separate times but their development time-scales overlap in the 2010s. The work includes electrification, resignalling, new rolling stock and station upgrades. According to Network Rail, the modernisation started in June 2010 and was due to end in 2017., electrification was complete as far west as Cardiff Central, and also from Reading to Newbury.
The project has been subject to repeated delays. In November 2016 the government announced that several major elements of the electrification programme would be indefinitely deferred because costs had tripled. The five sections that are delayed are:
Under the Intercity Express Programme, 21 electric Class 800 trains were ordered as replacements for the ageing InterCity 125 diesels. In May 2016, owing to delays in the modernisation project, it was confirmed that the new trains would be converted to 'bi-mode', meaning they can run on diesel fuel and electric overhead wire.

Historical background

At the start of the 21st century, the Great Western main line and the Midland Main Line were the last of the major main line routes in the UK using diesel as the main source of locomotive power. When the announcement was made in July 2009 to electrify the Great Western, it represented the first big rail electrification project in the UK for 20 years. The South Wales Main Line section of the GWML is set to be the first electrified cross-country railway line in Wales.
The plan to upgrade the rolling stock on the Great Western was included in the IEP announced in 2007, a Department for Transport led initiative to replace the ageing fleet of InterCity 125 and InterCity 225 train sets then in use on much of the UK rail network.

Electrification

Status

Passenger timetables introduced electric running from Paddington to Didcot in January 2018, and to Swindon and as far west as Bristol Parkway in January 2019. The same month saw electric services between Reading and Newbury. Electric running to Newport commenced in December 2019 and to Cardiff in January 2020. Work continues between Swindon and Chippenham.

Earlier work

Prior to 2009, the only electrified portion of the Great Western was between London Paddington and Airport Junction. This portion is equipped with a 25 kV AC overhead system which was implemented in 1997 in readiness for the Heathrow Express service commencing in early 1998. Electrification was extended from Airport Junction to under the Crossrail scheme. Further electrification west of Maidenhead was announced by the DfT separately, though the work west of Airport Junction and west of Maidenhead is likely to be undertaken as one scheme.

July 2009 announcement

The UK government first considered electrifying the Great Western between London Paddington and Bristol Temple Meads in a first phase, then electrifying the rest of the line between to at a later date. However, in July 2009, the Department of Transport under the then Labour Government, announced that there would be a £1bn programme to electrify the whole of the Great Western from London to Swansea as well as to Bristol Temple Meads. The Labour government claimed that the investment would pay for itself over a 40-year period.
The scheme announced by the government on 23 July 2009 stated that "work will begin immediately on the electrification of the Great Western main line between London, Reading, Oxford, Newbury, Bristol, Cardiff and Swansea, to be completed within eight years". The proposed electrified route included:
Estimates showed that the Hitachi Super Express trains could reduce journey times from London Paddington to Swansea by 19 minutes.
In an effort to minimise disruption during the electrification works, Network Rail developed new "factory engineering trains" to facilitate the process of installing overhead lines. There are three types of train: the first train will be used to install pylons, followed by a train to hang the wires and finally a train which will check the installation. The system was expected to be able to install of electrification in an eight-hour shift. The vehicles were supplied by German firm Windhoff.
In its initial survey, Network Rail identified 113 structures – mainly bridges and tunnels – which required modernisation. In subsequent surveys this increased to 137. The largest structure, the Severn Tunnel, has good clearances and is relatively easy to electrify.

Review and announcements after May 2010 general election

After the 2010 UK general election in May 2010, the Conservative–Liberal Democrat coalition placed all major government capital expenditure, including the Great Western electrification scheme on hold pending a return-on-investment review. In November 2010, Transport Secretary Philip Hammond gave the go-ahead for the lines from Oxford via Didcot to London and Newbury to London to be electrified in the next six years. Extension from Didcot to Swindon, Bath, Bristol and to South Wales would be dependent on a further assessment due in 2011 of the costs and implementation requirements of the IEP.
On 1 March 2011, Hammond announced that rail electrification from Didcot Parkway to Bristol Temple Meads and Cardiff Central would go ahead. The section linking Bristol Parkway and Bristol Temple Meads would also be electrified.
In March 2012, Amey plc was awarded a £700 million contract to undertake the electrification works.
In July 2012, the UK Government announced that the final portion of the Great Western from Cardiff to Swansea would be electrified. In addition, as part of the Electric Spine project, the line between Reading and Basingstoke would also be electrified at 25 kV AC OHL. The overhead electrification of the branches to Henley, Marlow and Windsor were also added to the scope of the project. However, the Marlow electrification has been postponed for the foreseeable future due to difficulties at Bourne End.
The new NR Series 1 overhead line equipment, designed and manufactured by Furrer+Frey, is a TSI compliant OLE design specified to allow multiple pantograph operation at 140 mph operation and is being installed using Amey plc's High Output Plant System and other conventional techniques. This is designed to allow Adjacent Line Operation where works can be carried out while trains operate on adjacent tracks. The HOPS has five sections, each of which handles a different aspect of the installation – these can be coupled together to work as one unit, or separated to work independently. The train will be maintained at the High Output Operations Base in Swindon, on the site of former sidings. HOPS will mix and lay of concrete per night, and all equipment and personnel will arrive at the site on board.
The HOPS train was operational by 2014, but had not reached full productivity due to. By 2015, completion of the electrification project had been delayed, reportedly 1 year behind schedule, with completion expected in 2017. Costs of the electrification were reported to have tripled from an estimated £640M to £1.74bn.

Reviews after May 2015 general election

2015

In June 2015, the International Railway Journal reported: "Britain's secretary of state for transport, Mr Patrick McLoughlin has asked Sir Peter Hendy to review Network Rail's 2014–2019 capital investment programme, known as CP5, and report back in the autumn". The report stated that costs had tripled from the £874M original estimate to £2.8bn, and was £1.2bn higher than the estimate made a year ago. The main part of the programme will go ahead as planned and should be delivered by March 2019, but the Cardiff to Swansea section will be delayed, to some time between 2019 and 2024.
Revised dates for the completion of electrification work were published in early 2016, with electrification to Cardiff via Bristol Parkway, and the connection to Newbury planned by December 2018; the branch to Oxford from Didcot by June 2019; and the branch to Bristol Temple Meads from Wootton Bassett sometime between February 2019 and April 2020.

2016

In November 2016, the government announced that electrification work on the sections from Oxford to Didcot Parkway, Bristol Parkway to Bristol Temple Meads, Thingley Junction to Bath Spa and Bristol Temple Meads, and branches lines to Henley and Windsor had been indefinitely deferred. For Oxford and Bristol, the deferral was due to imminent resignalling and remodelling of the existing track layout.

2017

In July 2017, it was announced that the Cardiff-Swansea electrification project had been cancelled and that bi-mode trains would be used on the route.

Resignalling

Current systems

The Great Western main line is currently equipped with colour light signalling common to the rest of the United Kingdom. At the time of the Ladbroke Grove rail crash, the ATP warning system was under trial. In response to that incident, it became a requirement for all First Great Western trains to be fitted with ATP.

Future systems

When the Department for Transport first released the train specification for the new trains for the IEP in November 2007, it was stated that the Great Western main line would be upgraded to ETCS level 2 and ERTMS Level 2 in-cab signalling. Some or all of the resignalling work will be carried out alongside the electrification work. Signalling Solutions is to resignal the 12 miles from Paddington to, including the Airport branch, as part of the Crossrail project.

Future control

Thames Valley

In November 2008, Westinghouse was awarded a £20M contract for a 30-month programme of signalling enabling work. Over a series of 12 commissionings, Invensys Rail will re-lock the existing Reading Station and Spur interlockings to three new WESTLOCK Interlocking units, re-control the remaining 18 relay interlockings and move signalling and telecommunications control from Reading Station to the new Thames Valley Signalling Centre at Didcot. The work culminates in a final commissioning, scheduled for 5 December 2010 and paves the way for future stages of the remodelling programme.
The Thames valley signalling centre will eventually replace older signalling control in the entire English Western region. The London area is due to switch over at the end of 2011, followed by the old Slough PSB area. Attention will then be given to abolishing Oxford, Swindon A, Bristol PSBs and the 1990s Swindon B IECC. This will be followed by the elimination of the 1980s PSBs at Westbury and Exeter, and the 1970s Plymouth PSB, the 1960s PSB at Gloucester as well as substantial semaphore signalling in Cornwall.

South Wales

The first phase of a £400M, ten-year resignalling scheme in South Wales by Network Rail was carried out on a stretch between Port Talbot and Bridgend in 2006 and 2007. The works provided a new turnback facility in both directions at Port Talbot Parkway if required. The renewals replaced an old British Railways Western Region NX panel installation, dating from 1963. Railway technology has evolved somewhat since 1963 and the renewals will make some signalling facilities redundant. Further signalling renewals are programmed for the Newport area, Cardiff and Port Talbot West.
The first phase of the Newport Area remodelling and resignalling began in 2009 and is expected to be completed by the end of 2010. The first phase covers the stretch of line between Patchway and Marshfield to the west of Newport. A new South Wales Control Centre, built on the eastern end of Canton Depot in Cardiff, opened in Spring 2009. The signals implemented in Newport Area resignalling phase 1 will be the first to have control transferred to the South Wales Control Centre and once Phase 2 of the Newport Area resignalling is complete in 2011, the Newport signalbox will be closed. Control will pass to the South Wales Control Centre for other parts of the south Wales network as resignalling progresses.

Rolling stock

Long distance inter-city services

Services from London Paddington to south west England and south Wales were served by Class 43 "InterCity 125" train sets, until 18th May 2019. The Intercity 125 trains were built between 1975 and 1982 and due to their age are to be replaced by new Hitachi Super Express train sets. The "Intercity 125" trains, now operating in shortened sets from Bristol and Cardiff, are one of the fastest trains on the Great Western, operating at ; the only faster services in the UK are on High Speed One from Eurostar and Southeastern with their Class 373s, Class 374s and Class 395s, which operate at, and respectively; the Class 390 'Pendolinos' on the West Coast Main Line and the InterCity 225 trains on the East Coast Main Line which are both capable of, restricted only by line speed. The new Super Express trains will have a top speed of but will be capable of with minor modifications. The upgrading of the signalling on the Great Western to in-cab signalling is one pre-requisite to allow the new trains to run at the higher speed. In the 2010 GWML RUS, Network Rail stated that linespeeds in excess of west of Reading would be "reviewed in line with electrification and resignalling opportunities as ERTMS becomes deployed across the RUS area" after Control Period 4.
The initial new Hitachi Super Express trains planned for the Great Western inter-city services will be Class 800 electro-diesel bi-mode trains capable of running on lines with and without overhead wires. This is because of the deferment of the electrification project. Despite the initial limit of 125 mph, the increased acceleration and operational efficiency are expected to decrease the journey time from London to Bristol Temple Meads by 22 minutes. The new Super Express trains will bring an estimated 15% increased capacity during the morning peak hours. The bi-mode trains will allow inter-city services to operate from London directly to locations in South Wales and southwest England, to which electrification does not extend under the current electrification proposals, like Carmarthen, Worcester, Gloucester, Cheltenham and the regions to the southwest of Bristol and Newbury. A portion of the fleet will be Class 802 trains, a more powerful variant of the Class 800 which will cope better with the gradients in Devon and Cornwall.
New servicing facilities for the new fleet of Inter-City Express trains will be developed at the London North Pole Depot, the Filton Triangle rail depot in Stoke Gifford and at Maliphant sidings in Swansea.

Thames Valley commuter services

commuter services from London Paddington to Reading and to Oxford are currently served by a combination of Class 165 "Network Turbo" and Class 166 "Network Express Turbo" three-car DMUs which are capable of operating at. These trains will be replaced by the new 45 Class 387 four-car trains currently used on Thameslink as an interim fleet. The Networker trains, electric versions of the class 165/166s, operated currently by Govia Thameslink Railway will not now cascade from Great Northern to the Thames Valley as originally planned. The plans were dependent on sufficient and s, replacing 365s and 387s on the Thameslink Great Northern network. The Network Turbo/Network Express Turbo trains would then be transferred for use for services in the Bristol and South West area.

Crossrail

The western section of Crossrail, to be known as the Elizabeth Line when opened in 2021, runs in part on the Great Western line. It will have 70 Class 345 trains which are formed of 9 carriages and can carry 1,500 passengers. These electric multiple units can achieve speeds of up to on the surface sections of the route and up to in the tunnels. These trains are being built by Bombardier Transportation at their Derby Litchurch Lane Works.

Station renovation and enhancements

Several stations along the Great Western are undergoing redevelopment or have recently been upgraded to cope with growing passenger numbers and to ease rail traffic congestion.

Bristol Temple Meads

will be expanded into Digby Wyatt's 1870s extension to the original train shed, built by Isambard Kingdom Brunel in 1840 as the terminus for the Great Western main line. This part of the 'Old Station' building is currently in use as a car park, but will be remodelled as terminating platforms for services to London Paddington. To achieve rail access to the existing old platforms the Bristol power box, opened in 1970 and controlling 114 route miles of track, will need to be decommissioned and demolished.

Bristol Parkway

had a new third platform completed in 2007 to provide a new platform for trains departing to London and Birmingham and to make services more reliable between London and south Wales. A new fourth platform has been built on the south side of the station.

Reading

On 10 September 2008, Network Rail unveiled a £400M regeneration and reconfiguration of Reading station and surrounding track, incorporating an overpass to the west of the station; with freight and passenger trains able to transit from the Reading to Taunton Line and Reading to Basingstoke Line to the 'slow' lines via an underpass beneath the 'fast' lines, replacing the conventional at-grade crossing of the 'fast' lines via points, with the aim of alleviating delays due to slow-moving freight service passing through the station. By 2014 the total cost had risen to more than £800M.
As well as the reconfiguration of the track, the terminal platforms for services to/from London Waterloo will be altered and the Cow Lane bridge under the tracks has been made two-way and now includes a cycle path. There will be improvements that will provide capacity for at least four extra trains in each direction every hour.
The station received:
These plans provide for the future Crossrail and possible Airtrack services at Reading station, building a railway that will be fit for at least the next thirty years. Also, the improvements will allow six new freight trains each day – this could take around 300 lorries a day off the roads.
While much of the work was carried out in 2010, trains to Devon and Cornwall ran from London Waterloo instead of Paddington, using the South Western Main Line via Basingstoke then the West of England Main Line and Wessex Main Lines. Trains to Bristol, South Wales and Cheltenham were diverted via the Chiltern Main Line where they reversed and returned via Oxford to Didcot Parkway, South Oxfordshire to re-adopt the Great Western main line.
As of February 2015, the regeneration and modernisation of Reading Station is complete. The station now has 15 platforms, each serving their own specialist destination and purpose. The new platforms allow more frequent trains to run through Reading and allow more passengers to join longer trains. The entire Reading Redevelopment project will be completed by 2017.

Didcot Parkway

An improvement programme for the forecourt of began in September 2012 and ran for two years. Features included:
In 2018, a new multi-storey car park started to be built at Didcot Parkway, over the west long stay carpark. It should be completed in the autumn of 2018 providing 1800 spaces, to reflect the station's role as a Park and ride facility for the surrounding area.

Newport

In 2009, an upgrade to Newport station was started to enable the station to cope with the expected passenger traffic associated with the 2010 Ryder Cup. A new passenger bridge and two new terminal buildings were constructed, with each platform being served by a lift. The new bridge is clad in ethylene tetrafluoroethylene, the material which protects the Eden Project in Cornwall, despite which the roof initially gave problems with leaking. The new development at the station includes a new multi-story car park and a new bus station will be developed outside, replacing the existing Newport bus station. The new north and south concourses opened on 13 September 2010. The development was criticised by Rail Magazine columnist Barry Doe for being at the wrong end of the station, having a leaking roof, a lack of seating and generally poor design.

Cardiff Central

Extra platform capacity at Cardiff Central will be introduced in the form of a new bay platform for services between Cardiff and Maesteg along the GWML and one new through platform to the south of the station for the Cardiff urban services to cater for up to 16 trains per hour. This will bring the number of platforms from 7 to 10. Redevelopment of Cardiff Central bus station outside the railway station commenced in 2008.

London Paddington

Between 2009 and 2015, a new Crossrail station was to be built under London Paddington, serving as a connection to National Rail services and London Underground. Services were due to start in 2018.
Network Rail had planned to demolish the arched section to the north-east of Paddington station, known as Span 4. Span 4 was an extension completed in 1916 and the roof had since become dangerous. An internal blanket was erected in the 1990s to protect people from falling glass. Span 4 was to be replaced by an office block over the rails but it was later decided that the structure would be restored. The restoration of Span 4 took place between 2009 and 2010, and it re-opened in late 2011, looking notably brighter than the other three spans of the station.

Port Talbot Parkway

Work on modernising Port Talbot Parkway station began in Autumn 2014. The old ticket office was demolished and a new footbridge built over the platforms. The footbridge will features a new ticket office and step free access to the platforms provided by lifts.

Severn Tunnel Junction

serves as a Park and Ride station for commuters from southern Monmouthshire to Bristol, Newport and Cardiff and there is a local action group – the Severn Tunnel Action Group – who are campaigning to enhance the Junction's status as a transport hub for the southern Monmouthshire area. As of January 2010, Network Rail have remodelled the tracks around the station, re-opened Platform 4 and modernised the parking and passenger facilities. The junction where the Gloucester to Newport Line joins the South Wales Main Line has been moved west of the station and now joins the main line with high-speed turnouts.

Swansea

A £7.6M modernisation of Swansea station began in 2011 and was completed in June 2012. The renovation work included enlargement of the concourse, cleaning of the front of the station with a new entrance, replacement of the partition wall between concourse and platforms with a glazed wall, a new café and more shops.

Developments on associated lines

Crossrail

is a major rail scheme, under construction since 2009, to provide a new east-west railway connection under Central London. The western portion of the line will connect with the Great Western main line to the west of Paddington. With electrification of the Great Western extended westwards past Reading, the Department of Transport stated that Crossrail will terminate at Reading. Some of the suburban services using the GWML into London Paddington will be transferred to Crossrail, which will free up capacity at the surface level station at Paddington.

Connection to Heathrow Airport: Western Rail Access Programme

The Western Rail Access Programme is a scheme under development by the DfT, Network Rail and local authorities near Heathrow Airport to develop a direct rail link to the airport from the west. At present passengers travelling from the west of Airport Junction need to change trains at either Hayes and Harlington or Paddington which are to the east of the junction. The proposed link will consist of a tunnel connecting a new junction between Langley and Iver stations to Terminal 5. The new link will enable direct rail services between Reading and the airport.
With the confirmed electrification of the Great Western main line west of Airport Junction, local authorities in the Thames Valley identified a case to be made for introducing a service to Heathrow Airport from Reading via the Great Western, which would also serve Maidenhead and Slough.
On 12 July 2012, Transport Secretary Justine Greening announced that a new rail link connecting Slough and Heathrow had been given the go-ahead and would be operational by 2021.

MetroWest

is a project to improve the rail services in Greater Bristol. It was first proposed at First Great Western's Stakeholder Event in March 2008. On 5 July 2012, the UK government and councils in and around Bristol agreed a City Deal whereby Bristol would have more funding for investment in the area. As a result of the City Deal, around £100M is expected to be invested in rail services under the Greater Bristol Metro scheme. As part of the work, the Cross Country Route between Bristol Parkway and Bristol Temple Meads, commonly known as Filton Bank, will be expanded from two to four tracks.

South Wales Metro

The South Wales Metro is a proposed integration of heavy rail and development of light rail and bus-based public transport services and systems in South East Wales around the hub of. The first phase was approved for development in October 2013.

Swindon–Kemble redoubling

The Golden Valley Line serves as a diversionary line for several other lines in the area as well as serving its normal traffic. It will be a major diversionary route during the electrification of the Great Western main line. The line between Swindon and Kemble was reduced to a single track in 1968, limiting its capacity. In his March 2011 Budget, the Chancellor George Osborne approved a project to re-double this section of line, after several years of campaigning by local politicians. The scheme was completed in August 2014.

Further electrification in south Wales

During his announcement on Great Western electrification in March 2011, transport secretary Phillip Hammond stated that a good business case existed for the electrification of several south Wales commuter lines. In July 2012, the UK Government announced that the south Wales commuter lines would be electrified. The lines which would be electrified are: all Valleys & Cardiff Local Routes, the Ebbw Valley Railway and the Maesteg Line.

Controversies

On infrastructure

Some press reports state that passengers face six years of disruption from the electrification work. Over 100 bridges and tunnels require demolition or modification to accommodate the new overhead lines.
The Goring Gap Railway Action Group has complained that there has been insufficient consultation between Network Rail and residents of Goring-on-Thames about the visual impact of the overhead line supports.
The footbridge at, South Gloucestershire, was demolished in 2016 because it was too low for electrification and the low passenger numbers did not justify a replacement. The removal of the footbridge meant that the station's westbound platform was no longer accessible and thus was closed. Campaigners alleged that the removal amounted to a closure by stealth, with Network Rail apologising for not consulting residents or conforming to their code of best practice. Geoff Marshall and Vicki Pipe visited Pilning in 2017 as part of their All the Stations project, attracting local media attention to the station's status. There was subsequently a campaign for Pilning to receive the footbridge from, following that station's closure in May 2019, but Network Rail stated that there was no financial justification for replacing the bridge. Local rail group Friends of Suburban Bristol Railways claim that Network Rail saved £658,000 by removing the bridge, and that a replacement would cost in the region of £5m–7m.

On rolling stock

The announcement of electrification of the Great Western led to the Government changing their plans to purchase a new fleet of diesel trains consisting of 202 locomotives and 1,300 train carriages. The RMT union called for assurances that the plans will not have an adverse impact on jobs at the UK's only train maker Bombardier.
In February 2010, it was announced that the IEP was suspended pending an independent report, with a decision on its viability to be given after the 2010 UK general election. In 2012 the contract to provide Intercity Express bi-mode trains was awarded to Hitachi.

Details of progress with infrastructure

Although the enabling work on the trackbed, platforms and bridges is now complete, the installation of the electrification equipment has been delayed on the sections between Chippenham, Bath Spa and Bristol Temple Meads and between Bristol Temple Meads and Bristol Parkway.
SectorLocationTypeProgressCompletion/Target DateDetails
Chippenham-----
Chippenham-BathBathTrack LevelComplete2015To clear Sydney Gardens bridges, Bath.
Bath-----
Bath-BristolBellotts overbridgeBridgeComplete2017Demolished, rebuilt. AKA Somerset & Dorset Intersect Bridge. Part of the Two Tunnels cycleway.
Bath-BristolKeynsham overbridgeTrack LevelComplete2016 AprClearance.
Bristol Temple MeadsRoyal Mail ConveyorRemovalCompleteN/KClearance.
Filton Bank-----
Lawrence Hill-Filton Abbey WoodLawrence Hill-Filton Abbey WoodTrackbedCompleteN/KTrackbed preparation and addition of two tracks, returning Filton Bank to a 4-track route.
Lawrence Hill-Filton Abbey WoodStapleton Road Station FootbridgeFootbridgeCompleteN/KReplace low footbridge
Lawrence Hill-Filton Abbey WoodMidland Railway BridgeOverbridgeComplete2016 MayProtect public from cables. The higher bridge sides now have a mural.
Lawrence Hill-Filton Abbey WoodEaston Road BridgeOverbridgeCompleteN/KReplace footbridge
Lawrence Hill-Filton Abbey WoodBonnington Walk roadbridgeOverbridgeCompleteN/KProtect public from cables